|
The Catalyst
Scheduler can be launched by selecting Planning > Generate
Finite Schedule. The finite scheduling engine creates a finite
capacity schedule based on the planned capacity reflected in the
shop calendar for each work center. The Schedule Direction
indicates whether the scheduler forward schedules from the shop
order release date or backward schedules from the due date. When
backward scheduling, the scheduler first attempts to schedule a
shop order using backward sequencing. If the resulting scheduled
start date is before the current date, the shop order is
rescheduled using forward sequencing. For bottleneck scheduling,
schedule the bottleneck operation manually using the Shop Order Master and select the Frozen flag. Then
select the ‘Backward’ schedule direction to backward schedule
preceding operations and forward schedule downstream operations
from the frozen operation.
The shop orders are
loaded into the schedule according to job selection rules. The
shop orders can be sorted according to Due Date, Critical Ratio,
or Priority job selection rules. These three job selection rules
are defined below.
Due Date: shop orders are
loaded onto the Production Scheduling Board beginning with the
earliest shop order due date. The shop order number is used as
secondary sort criteria in the event of a tie.
Critical Ratio: shop orders are
loaded onto the Production Scheduling Board beginning with highest
critical ratio. The critical ratio is calculated by dividing the
hours remaining to be completed on the shop order operations by
the shift hours remaining on the shop calendar before the due
date. The due date and shop order number are used as secondary
sort criteria in the event of a tie.
Priority: shop order priorities
range from 1 to 50 with 1 being the highest priority and 50 the
lowest priority. Shop orders are loaded onto the Production
Scheduling Board beginning with highest priority (1) and ending
with the lowest priority (50). The shop order priority defaults to
50 and can be changed either on the Shop Order Master or the
Capacity Planning window. The due date and shop order number are
used as secondary sort criteria in the event of a tie.

To apply campaign rules to the
scheduling process, select the appropriate option under the
Campaign Rules group. The application of campaign rules allows
the scheduler to consider efficiencies in sequencing operations to
minimize setup time and maximize resource capacity. The campaign
rules are applied when sequencing operations of the same item or
product family. The Catalyst Scheduler will apply campaign rules
only to operations with the Campaign flag marked on the shop order
route. When the ‘Apply to same product only’ option is selected,
the setup hours for a shop order operation is assumed to be zero
when the prior operation on the work center resource is the same
item. When the ‘Use product family setup matrix’ option is
selected, the setup hours for a shop order operation is obtained
from the Product Family Setup Matrix. The setup hours used for the
operation is based on the product family of the previously
scheduled item and the product family of the current item.
You can select whether to include only
released shop orders or both open and released shop orders in the
production schedule by marking the appropriate check box in the
Order Status section. To calculate the scheduled start and
finish dates for an individual shop order, select the shop order
from the drop-down list in the CTP Calculation section.
After the schedule is generated, the scheduled start and finish
dates are displayed for review. The shop order start and finish
dates can be frozen by clicking the Freeze button located
in the section.
The Catalyst Scheduler only schedules
unfrozen shop order operations. Prior to generating a new
production schedule, the operations in the current schedule can be
frozen to prevent them from being changed after they are released
to the shop floor for production. The options in the Schedule
Control section allow the scheduler to freeze all operations,
scheduled operations, or started operations for both open and
released shop orders operations. The same options are provided for
unfreezing any frozen operations. To leave the frozen status of
operations unchanged, use the default No Action option. The
Late Shop Orders Report in the Production menu can
be used to review shop orders with scheduled finish dates beyond
the due date.
|