The
Production Schedule Board is useful for quickly assessing
the performance of the production schedule and making
fine-tune schedule adjustments prior to releasing shop orders
to production. The Production Schedule Board can be opened
from the Production menu and displays the finite
capacity schedule in Gantt chart view with each row containing
scheduled shop order operations for a work center resource
across time.
The Production
Schedule Board displays work non-work periods in a yellow
background based on the planned capacity in the Shop
Calendar. The shop order operations appear as red (late)
or blue (on-time) bars with each one labeled with the shop
order number and sequence number. The length of the operation
bar represents its duration with the beginning and end of the
bar representing the schedule start and finish times. An
operation that must span over non-work periods will appear
longer than the actual operation hours required.
The Production
Schedule Board can be used an effective tool to quickly
reschedule shop order operations and obtain a frozen schedule
that will not be changed by the addition of new orders into
the system. An operation can be rescheduled by dragging an
operation bar to another work period on the same resource.
Rescheduling operations on the scheduling board changes the
schedule start and end dates and times for the operation and
freezes the operation so that it will not be rescheduled the
next time the scheduler runs. To allow the scheduler to make
adjustments to the overlap between operations, the
rescheduling of one operation on a shop order will not
automatically move other operations on the same shop order. To
move multiple operations on the same shop order, drag and drop
each individual operation. To highlight all operations on a
shop order, click the Select S.O. toggle button. To
remove the highlight from a shop order, turn off the toggle
button. |